Friday, 22 January 2010

Action plan


23rd - 29th January ( 1 week ) :

Developing our ideas for stories and deciding what one we want to do

Sorting out people to use in our filming

Getting all audience research collected
- interview with friends

- showing openings of films with feedback on them

- questionnaires / surveys
29th - 2nd February ( 5 days ) :

Developing our chosen storyline; developing our characters and their personalities
Decide what camera angles and shots we want to incorporate within our piece
Coming up with a storyboard for our opening sequence

2nd - 5th February ( 4 days ) :

Planning music to use in our piece
Scripting dialogue that we want to have

5th - 12th February ( 8 days ) :

Sorting out the mise en scene
- Lighting/Colour
- Positioning within the scene
- Facial expressions and body language
- Costumes
- Props/Settings
12th - 22nd February ( 2 weeks ) :

Filming :)

22nd - 1st March ( 1 week ) :

Importing all the filming we already have and sorting it out to see whether there are things we need to reshoot or add to give us more to work with

1st - 19th March ( 19 days ) :

Reshooting and importing all the new stuff if needed
Choosing all the parts of filming we want to work with etc getting them ready to edit
Editing into final piece

19th - 30th March ( 12 days ) :

Evaluating project and final piece